2012 -
[
 Huntmar Road new sidewalk
](http://ottawastart.com/theyre-finally-adding-a-sidewalk-sort-of-to-huntmar-road/)
- between Palladium and Huntmar

 * 
2012 - Stittsville Main new sidewalk - between Fernbank and Brigade

 * 
2014 - Campeau Drive extension - Didsbury to Huntmar

 * 
2016 - Carp Road widening - 417 to Hazeldean

 * 
2016 - Palladium Drive realignment - Huntmar to future north-south arterial

 * 
2017 - Huntmar Road widening - Campeau to Cyclone Taylor and Palladium to Maple Grove

 * 
2018 - Kanata West Main Street - Maple Grove to Palladium

 * 
2018 - Kanata West north-south arterial - Hazeldean to Fernbank

 * 
2019 - Terry Fox Drive widening - Winchester to Eagleson

 * 
2023-2031 - Kanata West north-south arterial - Huntmar to Hazeldean

 * 
2023-2031 - Maple Grove widening

 * 
Prior to 2031 - West Transitway connection - Terry Fox to Fernbank